Mosaic Belle Plaine Pond Feeder Replacement
Included in this project was approximately 3.5km of 750mcm/3c 25kv Airguard cable and fibre optic cable to replace the existing aging cabling. This project was very complex, simply based on the fact that in approximately a 1km area we had 90 utility crossings to execute; the project was completed without any incidents. Also completed on this site, fire alarm detection systems, as well as Sapphire system and thermowire detection system installations. This project was managed directly by Mosaic Belle Plaine.